How to Run Full Planning, MPS and MRP | Microsoft Docs

The terms "running the planning worksheet" or "running MRP" refer to the calculation of the master production schedule and material requirements based on actual and forecasted demand. The planning system can calculate either Master Planning Schedule (MPS) or Material Requirements Planning (MRP) on request, or it can calculate both at the same time.

The planning algorithms used for both MPS and MRP are identical. The planning algorithms pertain to netting, reuse of existing replenishment orders, and action messages. The planning system process examines what is needed or will be needed (demand) and what is on-hand or expected (supply). When these quantities are netted against each other, Business Central provides action messages. Action messages are suggestions to create a new order, change an order (quantity or date), or cancel an order already on order. The term "order" includes purchase orders, assembly orders, production orders, and transfer orders.

Links created by the planning engine between demand and its related supply can be tracked on the Order Tracking page. For more information, see Track Relations Between Demand and Supply.

Proper planning results depend on the set up done on item cards, assembly BOMs, production BOMs, and routings.

Methods for Generating a Plan

With each planned method, Business Central generates worksheet entries assuming infinite capacity. Work center and machine center capacity is not considered when you develop schedules.

IMPORTANT

The Calculate Regenerative Plan function is the most common process. The Calculate Plan and Carry out Action Messages functions, however, can be used to run the Calculate Net Change Plan process.

The Get Action Messages Plan function can be run between regenerative and net change planning runs to obtain an immediate view of the effect of schedule changes, but it is not intended as a replacement of full regenerative or net change planning processes.

To calculate the planning worksheet

  1. Choose the Lightbulb that opens the Tell Me feature icon, enter Planning Worksheets, and then choose the related link.
  2. Choose the Calculate Regenerative Plan action to open the Calculate Plan page.
  3. On the Options FastTab, fill in the fields as described in the following table.

    Field Description
    MPS Select to initiate the calculation of a master production schedule. Items with open sales orders or demand forecasts are considered in this run.
    MRP Select to initiate the calculation of material requirements planning. Items with dependent requirements are considered in this run. Typically, MPS and MRP are run at the same time. To run MPS and MRP at the same time, the Combined MPS/MRP Calculation field must be selected on the Planning FastTab on the Manufacturing Setup page.
    Starting Date This date is used to evaluate inventory availability. If an item's on-hand quantity is below the reorder point, the system forward-schedules a replenishment order from this date. If an item is below its safety stock (as of the starting date), the system back-schedules a replenishment order due on the planning starting date.
    Ending Date This is the ending date of the planning horizon. Neither demand nor supply is considered after this date. If the reorder cycle for an item extends beyond the ending date, the effective planning horizon for that item is equal to the order date + reorder cycle.

    The planning horizon is the time that the plan is extended to. If the horizon is too short, items with a longer lead time are not ordered on time. If the horizon is too long, too much time is spent reviewing and processing information that likely changes before it is needed. It is possible to set one planning horizon for production and a longer one for purchases, although it is not required. A planning horizon for purchases and production should be set to cover the cumulative lead time for components.
    Stop and Show First Error Select if you want the planning run to stop as soon as it encounters an error. At the same time, a message is displayed with information about the first error. If an error exists, only the successful planning lines made before the error was encountered will be presented in the planning worksheet. If you do not select this field, the Calculate Plan batch job will continue until it has completed, that is, errors will not interrupt the batch job. If one or more errors exist, a message will display after completion with information about how many items are affected. The Planning Error Log page will then open to provide more details about the error and links to the affected item cards.
    Use Forecast Select a forecast that should be included as demand when you run the planning batch job. The default forecast is set up on the Planning FastTab on the Manufacturing Setup page.
    Exclude Forecast Before Define how much of the selected forecast to include in the planning run by entering a date before which forecast demand is not included, thus allowing you to exclude old information.
    Respect Planning Parameters for Exception Warnings By default, this field is selected.

    Supply on planning lines with warnings is normally not modified according to planning parameters. Instead, the planning system only suggests a supply to cover the exact demand quantity. However, you can define certain planning parameters for planning lines to be respected with certain warnings.

  4. On the Item FastTab, set filters to run the planning based on item, item description, or location.

  5. Choose the OK button. The batch job runs and then the planning worksheet is populated with the planning lines.

To perform action messages

  1. On the Planning Worksheet page, choose the Carry Out Action Message action.
  2. On the Options FastTab, specify how to create the supplies. Fill in the fields as described in the following table.

    Field Description
    Production Order Specify how you want to create production orders. You can do this directly from the planning line proposals. You can create either planned or firm planned production orders.
    Assembly Order Specify how you want to create assembly orders. You can do this directly from the planning line proposals.
    Purchase Order Specify how you want to create purchase orders. You can do this directly from the planning line proposals.

    If you chose to copy the planning line proposals for purchase orders to the requisition worksheet, select the template and worksheet name.
    Transfer Order Specify how you want to create transfer orders. You can do this directly from the planning line proposals.

    If you chose to copy the planning line proposals for transfer orders to the requisition worksheet, select the template and worksheet name.
    Combine Transfer Orders Select if you want to combine transfer orders.
    Stop and Show First Error Select if you want the Carry Out Action Msg. - Plan. batch job to stop as soon as it encounters an error. At the same time, a message is displayed with information about the firsterror. If an error exists, only the planning lines processed before the error was encountered will create supply orders.
  3. On the Planning Line FastTab, you can set filters to limit the perform action messages.

  4. Choose the OK button.

The batch job deletes the lines in the planning worksheet after it has performed the action message. The other lines remain in the planning worksheet until they are either accepted at a later date or else deleted. You can also delete the lines manually.

Action Messages

Action messages are issued by the order tracking system when balance is unattainable in the existing order network. They can be viewed as a suggestion for you to process changes that reestablish equilibrium between supply and demand.

The generation of action messages occurs one level at a time, for each item's low-level code. This makes sure that all items that experience or will experience changes in supply or demand are considered.

To avoid small, superfluous, or unimportant action messages, the user can establish dampeners, which serve to restrict the generation of action messages to only those changes that exceed the defined quantity or number of days.

After you have reviewed the action messages and determined whether to accept some or all of the suggested changes, select the Accept Action Message field, and then you are ready to update the schedules accordingly.

NOTE

An action message is a suggestion to create a new order, cancel an order, or change the quantity or date of an order. An order is a purchase order, transfer order, or production order.

In response to any supply/demand imbalances, the following action messages are generated.

Action Message Description
New If a demand cannot be fulfilled by suggesting action messages to Change Qty., Reschedule, or Reschedule & Change Qty. on existing orders, the action message New is generated, which suggests a new order. In addition, the message New is generated if there are no existing supply orders in the reorder cycle of the item in question. This parameter determines the number of periods forward and backward in the availability profile when it searches for an order to reschedule.
Change Quantity When demand that is tracked to a supply order experiences a quantity change, the action message Change Qty. is generated, which indicates that the related supply should be changed relative to the change in demand. If a new demand emerges, Business Central searches for the nearest existing unreserved supply order in the reorder cycle, and issues a change of action message for that order.
Reschedule When a supply or demand order experiences a date modification causing an imbalance in the order network, the action message Reschedule is generated. If there is a one-to-one relationship between demand and supply, an action message is generated suggesting that the supply order be moved accordingly. If the supply-order covers demand from more than one sales order, the supply order is re-scheduled equal to the date of the first demand.
Resch. & Chg. Qty. If both the dates and quantities of an order have been modified, you must change plans with regard to both circumstances. Action messaging gathers both actions in one message, Resched. and Chg. Qty., to ensure that the order network returns to balance.
Cancel If a demand, which has been covered on an order-to-order basis, is deleted, an action message is generated to cancel the related supply order. If the relationship is not order-to-order, an action message is generated to change in order to reduce the supply. If through other factors, such as inventory adjustments, a supply order is not required at the time the action messages are generated by the user, Business Central suggests an action message of Cancel in the worksheet.

See Also

Planning
Setting Up Manufacturing
Manufacturing
Inventory
Purchasing
Design Details: Supply Planning
Setup Best Practices: Supply Planning
Working with Business Central



© 2019 Microsoft. All rights reserved.